Executed projects

Infrastructure and environmental protection

Complete works of the objects shell including a reinforcement assembly for sewage treatment plant modernization, located on the borders of Chorzow and Katowice with a capacity of 110 thousand. Cu.m. per day and more than 250 000 ENI.

Scope of works: - Septic tanks
- Pumping station
- Engine and boiler rooms

Client: Budimex SA Localization: Chorz闚
Execution period: 01.2010 – 06.2010 Contract net value: < 5 mln PLN Reinforced concrete works: 4400 m3
Contract for the implementation of the motorway ring road of Wroclaw. Concrete works for the viaduct with a length of 64 m. Scope of works: installation of formworks on girders, installation of anchors with cementation and concrete paving. A whole range of tasks has been completed in four months.
Client: Budimex SA Localization: Wroc豉w
Execution period: 08.2009 – 12.2009 Contract net value: < 5 mln PLN Lenght: 64 m
Height: 6,5 m
Reinforced concrete works: 700 m3
Complete concrete work for the construction of municipal sewage treatment plant in Ogrodzieniec. Daily capacity of the facility is 500 cu. m. and ENI ratio about 8300. It is worth noting that the realization of the tasks took place in difficult geological conditions and need of ground water reduction by 2 m.
Client: AWBUD Design & Build Localization: Ogrodzieniec
Execution period: 08.2006 - 11.2007 Contract net value: < 5 mln PLN
Comprehensive reinforced concrete works for most of the new sewage treatment facilities has been executed, i.e.: grid building and reservoirs, three warehouses, workshop and warehouse building, two pumping stations and administration building.
Client: AWBUD Design & Build Localization: Piekary 奸御kie
Execution period: 12.2007 - 10.2009 Contract net value: < 20 mln PLN
- Urz康 Miasta Wolbrom - reinforced concrete water tank in Por瑿a - Dzier積a,
- Sewage treatment plant in Zawiercie - fermentation chamber - reinforced concrete structure,
- III-storey high garage building in Lublin,
- A-4 highway - Southern ring road of Kraków - reinforced concrete tunnel
2010 - 2012 AWBUD 浩LBET. Wszelkie prawa zastrze穎ne